5-Bedroom Family Villa
Fumba, Zanzibar
Location
Fumba, Zanzibar
Budget
$195,000
Timeline
16 weeks
Client
Fatima & Ali Rashid
Project Overview
280 sqm family villa — aluminium windows, kitchen cabinets, 6kW solar system, full tiling and painting
The Challenge
Managing a full villa fit-out from Dubai with bimonthly visits. Material approvals happening remotely across multiple phases.
Our Solution
Phased installation aligned to visit calendar. Materials pre-approved via WhatsApp. Dedicated coordinator with weekly progress reports.
Timeline
Project completed in 16 weeks — January 2025.
- Project kick-off and site assessment
- Materials procurement and team mobilisation
- Active construction phase
- Quality inspection and handover
Results
Completed in time for family relocation. 6kW solar system sized for full backup. Saved 6+ flights to Zanzibar during the build.
Project Gallery
Before → Completed


Construction Progress


— Fatima & Ali Rashid