Warehouse & Office Complex
Commercial

Warehouse & Office Complex

Kiwengwa, Zanzibar

Location

Kiwengwa, Zanzibar

Budget

$420,000

Timeline

14 weeks

Commercial Developer · Zanzibar

Client

ZanTraders Group

Project Overview

800 sqm steel-frame warehouse with attached 200 sqm office — structural steel, concrete floors, aluminium windows, electrical, plumbing, security

The Challenge

Rapidly growing trading company needed warehouse and office space completed before peak import season. Imported steel had customs delays that compressed the build timeline.

Our Solution

Pre-engineered steel frame designed for fast assembly. Concrete slab poured in single continuous operation. Customs coordination team expedited steel release. Parallel interior fit-out schedule.

Timeline

Project completed in 14 weeks — December 2024.

  • Project kick-off and site assessment
  • Materials procurement and team mobilisation
  • Active construction phase
  • Quality inspection and handover

Results

Warehouse operational in 14 weeks despite 3-week steel delay. 800 sqm of covered storage with mezzanine office. CCTV and access control integrated from day one. Developer already planning phase two expansion.

Project Gallery

Before → Completed

Warehouse & Office Complex — Completed
Warehouse & Office Complex — Before
BeforeCompleted

Construction Progress

Warehouse & Office Complex — Structure
Structure
Warehouse & Office Complex — Installation
Installation
Warehouse & Office Complex — Finishing
Finishing
“The steel delay could have killed the project. Zanzibaba reorganised the entire schedule around it and still delivered on time. That's the kind of problem-solving you need in Zanzibar.”

— ZanTraders Group