Warehouse & Office Complex
Kiwengwa, Zanzibar
Location
Kiwengwa, Zanzibar
Budget
$420,000
Timeline
14 weeks
Client
ZanTraders Group
Project Overview
800 sqm steel-frame warehouse with attached 200 sqm office — structural steel, concrete floors, aluminium windows, electrical, plumbing, security
The Challenge
Rapidly growing trading company needed warehouse and office space completed before peak import season. Imported steel had customs delays that compressed the build timeline.
Our Solution
Pre-engineered steel frame designed for fast assembly. Concrete slab poured in single continuous operation. Customs coordination team expedited steel release. Parallel interior fit-out schedule.
Timeline
Project completed in 14 weeks — December 2024.
- Project kick-off and site assessment
- Materials procurement and team mobilisation
- Active construction phase
- Quality inspection and handover
Results
Warehouse operational in 14 weeks despite 3-week steel delay. 800 sqm of covered storage with mezzanine office. CCTV and access control integrated from day one. Developer already planning phase two expansion.