Zanzibaba.Project Solutions
Resort Solar & Backup Power System
Hotels

Resort Solar & Backup Power System

Nungwi, Zanzibar

Location

Nungwi, Zanzibar

Budget

$145,000

Timeline

6 weeks

Hotel Operator · Nungwi

Client

Blue Bay Resort

Project Overview

40kW solar PV system, 60kWh battery storage, generator auto-transfer switch for 30-room resort

The Challenge

Resort experiencing daily power cuts during peak season, losing revenue from room cancellations and food spoilage. Needed a seamless backup solution that required no guest interaction.

Our Solution

Hybrid solar system with automatic transfer switching. Battery bank sized for overnight guest loads. Generator integration for extended cloudy periods. All switchgear hidden from guest areas.

Timeline

Project completed in 6 weeks — November 2024.

  • Project kick-off and site assessment
  • Materials procurement and team mobilisation
  • Active construction phase
  • Quality inspection and handover

Results

Zero guest disruption from power cuts. Resort now runs on solar during daylight, battery through evening peak, with generator as emergency backup. 60% reduction in generator fuel costs.

Project Gallery

Before → Completed

Resort Solar & Backup Power System — Completed
Resort Solar & Backup Power System — Before
BeforeCompleted

Construction Progress

Resort Solar & Backup Power System — Structure
Structure
“Our guests never notice the power cuts anymore — the system switches so smoothly you can't tell. Best investment we've made.”

— Blue Bay Resort