Project Overview

12-room boutique hotel — full renovation of 3 floors, new aluminium windows, updated MEP, rooftop terrace

The Challenge

Operating 150-year-old Stone Town building with heritage restrictions. Needed modern amenities (AC, en-suite bathrooms, reliable power) without altering the historic coral-stone façade or carved wooden doors.

Our Solution

Heritage-sensitive installation: aluminium windows set behind existing wooden shutters, concealed conduit for wiring, mini-split AC units hidden in bespoke joinery, rooftop services enclosure out of sight lines.

Timeline

Project completed in 12 weeks — July 2024.

  • Project kick-off and site assessment
  • Materials procurement and team mobilisation
  • Active construction phase
  • Quality inspection and handover

Results

All 12 rooms upgraded without heritage violations. Guest satisfaction scores increased from 3.8 to 4.6 stars. Occupancy up 35% post-renovation. Zanzibar Department of Antiquities approved all work.

Project Gallery

Before → Completed

Heritage Hotel Renovation — Completed
Heritage Hotel Renovation — Before
BeforeCompleted

Construction Progress

Heritage Hotel Renovation — Structure
Structure
Heritage Hotel Renovation — Installation
Installation
Heritage Hotel Renovation — Finishing
Finishing
“They understood Stone Town construction — how to modernise without destroying what makes this building special. The Department of Antiquities complimented the work.”

— Mtoni Palace Hotel